Construction and installation plan
minutes 28.8.203 meeting
Detector assembly
- Bus bars are ready on beam-pipe are ready. One more check requested: see if all the detector side pins fit.
- BOSSL ring and board (with cables) preferably installed before SciFi cooling block.
- Vertex detector helium ducts do not need to be installed before the SciFi ring, need to practice once at the Mockup
- We can install the ducts, BOSSL ring, & SciFi cooling block on a work bench, and install the assembly on the cage. Checked with AH if that is still OK for alignment.
- When we are installing first vertex & SciFi hardware, also have outer pixel hardware (e.g. end rings) around to practice and find conflicts.
- The HYDRA should not be one piece. Check with Matt.
- The outer pixel and Tile end-ring fit over the SciFi cooling block. It is not clear yet whether this is the case with all the uTP bundles in place. Possible conflict in the installation sequence.
- SciFi needs to be lowered slowly while handling the cables
- Vertex detector needs protection during SciFi installation.
- when does the HYDRA goes into position? We can not cover the bus bars before the SciFi detector is installed. Possible conflict in the installation sequence.
- At some point the location of the uTP bundles need to be assigned (one of the 3 channels)
Power, end-wheel, flanges
- Do we have a final uTP bundle length now? LV and FW measured once 116 cm to the reference point https://elog.psi.ch/elogs/Pixel/34, TR claims 140cm total length is fine. Do we have enough slack then?
- Need uTP support structure on the beam pipe
- Power crate:
- Need to do a cooling test once SM does a full run of the cooling water
- Need to fix the LV cable lengths
- Need to make an LDO board (FW)
- We need final HV crate
Helium ducts and SciFi cooling lines
- Current (small) helium duct design with interfaces has ~20 mBar pressure drop. Probably acceptable. New baseline. Needs to be confirmed with simulation and need to add the pressure drops of the HYDRA/End-ring and detector
- With 3.8 mm ID the pipe pressure drop is 0.42 Bar, and with 5 mm ID, this number because 0.12 Bar. This has to be compared to the Cooling ring pressure drop of 0.35 Bar
- 3.8 mm is too thin
- 5 mm ID works, but might be overkill
- Need one more iteration with a thinner section along the beam pipe (thinner walls?) and run the simulation.
- We will meet in HD in ~weeks for a cabling testing with 5 & 6 mm OD pipes, new Hedlium ducts, and uTP cables.
- DS there is no need for optimized pipe diameter. 6mm OD is fine.
- We need to prevent the helium flow from the HYDRA going under SciFi detector.
- We need to protect SciFi cooling structure from the outer pixel helium flow.
Staging area
- The stating cage has M6 holes for mounting tools. It is up to the sub detectors to make there assembly tools
- SciFi and Tile detectors need Chiller for staging area / detector tests. In principle a SMC chiller may become available if we crane the Platform 2 helium chiller back and forth, but this dance is heavely disfavored. We prefer a Huber chiller with the same interface. How much does the cheapest Huber chiller with the same interface cost?
- We could order this chiller together with the Helium system unistat.
- Helium piping needs to be improved.
SSW
- Priority after beam-pipe (with cooling block and Tile cooling distribution ring) is ready
- Assembly and cooling test in HD with a full SSW planned end of September.
- Plan a Infrastructure installation week at PSI (with HD engineers) , eying somewhere in November. Beam pipe can be installed earlier.
Staging area
- MT is very much occupied with Area work
- Need to fix and install piping electronic cooling piping (with valves at the right places foreseen)
Flange
- Need to communicate the desired Demaco interface to MT