09:00
Welcome
-
Cigdem Özkan Loch
(PSI - Paul Scherrer Institut)
-
09:10
The SLS 2.0 Booster-to-Ring Transfer Line - Design Criteria, Diagnostics Layout and Beam Results
-
Volker Schlott
(PSI - Paul Scherrer Institut)
-
09:35
Overview of SLS 2.0 Commissioning
-
Felix Armborst
(PSI - Paul Scherrer Institut)
-
10:00
Commissioning of SLS 2.0 BPM and Fast Orbit Feedback System
-
Boris Keil
(PSI - Paul Scherrer Institut)
-
10:25
SLS 2.0 MPS Commissioning and First Operation Experience
-
Felix Armborst
(PSI - Paul Scherrer Institut)