Attendees:
Mariia, Carlo, Alexandre, Marco, Paolo and Tom
Notes and Actions
Modulator
- Need to confirm with Roger that two modulators can fit in position of previous gun modulator (Action: Mariia)
Table
- Table will be magnetic but this appears to be fine according to measurements performed by Carlo.
- Table is 3.3 x 1.5 x 1.075m (LxWxH)
- Mariia needs drawing of table legs (Action: Carlo or Alexandre to have Rafael to send to Mariia)
- Cable tray and power box needs to be removed before installation. We'll aim to install when the bunker is finished with operation. (Action: Tom to put in list of actions for September)
Laser incoupling
- We're aiming for a 60 cm laser incoupling (Action: Carlo to understand laser requirements for this and Action: Tom to check beam size)
- FERMI style laser incoupling (Action: Paolo to ask for drawing and Step file from FERMI)
Layout
- Need to generation a holy list (Action: Tom)
- We focus on requirements for the FCCee measurements for now. If the chirping cavity is an issue for 5 nC this can be removed for the intial tests and we can design a SwissFEL+ version concurrent to other activities.
- We should clearly define which cable ducts are used for which services. (Action: Tom)
- Check about availability of girders (Action: Tom and Paolo to discuss with John Wickström)
Project introduction
- We'll aim to present within the RF Section by the end of April (Action: Tom to make slides)
- Present to whole project to CAS and some CPS people by Mid May (Action: Tom to make slides)
- Present in phases
Budget
- Alexandre to send Tom Budget of Laser (Action: Alexandre)
Components needed
- C-band phase shifter
- Variable power splitter or RF Switch
Controls
- Carlo to send Tom list for controls group (Action Carlo)
- Tom to fill in from electron beamline side. (Action Tom)
Infrastructure
- Need a new network swtich in the future
-
Documentation
- Could be good to write a CDR
- Create a folder for all documentation (Action Tom)