Pixel Production (VTX+OP)
→
Europe/Zurich
Description
Zoom [link] Task tracking: [Mattermost Board]
Key Points
- Proceed with mechanical ladders for bond optimisation rather than forcing through electrical ladder bonding with new HDIs, to avoid ambiguous results
- Plasma-clean remaining chips on mechanical ladder to test whether contamination is the root cause
- Stiffener prototype delivery from Adam's team remains delayed.
- Bond optimisation study on interposer flex completed successfully; new HDR showed no meaningful difference from old
- Wider traces on Version 5 HDI confirmed effective — no trace breaks observed
- Vertex HDI review finalised and approved; photo mask briefing initiated with LTU
- Matt built and installed a new module in the QC box; new clamp design reported to work better
- Probe card commissioning in progress: contact resistance needles with LED diode logic verified functional
- Unencapsulated ladder reached ~3,500 thermal cycles and is beginning to fail (well beyond required cycles), summary to follow
- Heidelberg cleanroom now clean; equipment being moved back in under controlled conditions
- Zurich (UZH) QC setup using VNA to measure V1 uTP cables; infrastructure ready, setup expected online next week (Thomas+student)
Blockers
- Inconsistent chip bonding (suspected contamination) → Alex to investigate via plasma cleaning before bonding electrical ladder
- Stiffener prototypes not yet delivered — Adam's team struggling with flatness and stiffness; timeline uncertain
- FPGA communication issue when testing new probe card → Aliki + Mark debugging
- Upstream connectivity missing on newly mounted module → Matt to retry when back next week
Pending Confirmation
- Whether Sultan will take on interposer flex PCB design work (Oxford internal discussion first)
- Carbon fibre DMA mechanical test study not yet done by Todd's team; only re-verified storage condition
- New engineering integration meeting proposed for Tuesday's (starting 17 November?), 2 PM UK / 3 PM CET — to be confirmed by Robert
- Thermal cycling studies of encapsulated bonds on ladder deprioritised until HDI qualification (and bond optimisation) is complete
Action Items
- Luigi: Contact supplier to initiate endpiece reorder paperwork
- Ashley/Alex: Continue pressing Adam's team on stiffener delivery before Christmas
- Matt (on return): Retry upstream connectivity check on newly mounted module in QC box
There are minutes attached to this event.