Progress with hiring of research associate [personnel topics excludes from meeting minutes]
Presentation of project structure (see attached diagram).
Project is divided into work packages:
-
WP e-Beam
-
WP Structure
-
WP Experiment
-
WP Hardware
-
WP Installation
-
WP Laser
-
WP Safety
-
WP Future projects
Discussion: combine all future projects into one work package
Meeting schedule
-
Bi-weekly core team meeting (scientific topics, topics of general interest)
-
Bi-weekly technical meeting (topics relevant to the installation)
IT
-
mail list
-
indico
-
SwitchDrive
Discussion: structures
-
Need input from collaborating partners on geometry of accelerating structure
There are minutes attached to this event.