Ultramagnetron midterm review
www.ultramagnetron.org/
Days: 4./5. October
Place: Seminar Hotel Stoos, Room Grosser Mythen
Participants: Project leaders Ultramagnetron, Coordinator, Daily Manager, EC Officer
Monday, October 4th
Sub-Premeeting by Nijmegen, Kaiserslautern, Würzburg and PSI
Time: 15:00 – 18:00 (meeting in the Hotel lounge)
Tuesday, October 5th
Midterm review
08:30-08:40 Welcome, introductions (Theo Rasing)
08:40-09:10 Project Controller: Financial reporting to the EU
9:10 - 11:10 Workpackage 1
- 9:10-9:40 Daily manager. Presentation of the progress until now. Its critical assessment.
9:40-10:00 Coffee break
- 10:00-10:20 Referee. Criticism of the Referee
- 10:20-10:50 Response of the consortium partners involved in the workpackage (Nijmegen, York, Konstanz, Kaiserslautern, Wurzburg ~ 10 min per partner)
- 10:50-11:10 Summary of the criticism. Development of updated time-table for deliverables
11:10-15:00 Workpackage 2
- 11:10-11:40 Daily manager. Presentation of the progress until now. Its critical assessment.
- 11:40-12:00 Referee. Criticism of the Referee
12:00-13:30 LUNCH
- 13:30-14:30 Response of the consortium partners involved in the workpackage (Nijmegen, York, Konstanz, Kaiserslautern,PSI ~ 15 min per partner)
- 14:30-15:00 Summary of the criticism. Development of updated time-table for deliverables
15:00-15:30 Coffee break
15:30-16:40 Workpackage 3
- 15:30-15:50 Daily manager. Presentation of the progress until now. Its critical assessment.
- 15:50-16:10 Referee. Criticism of the Referee
- 16:10-16:30 Response of the consortium partners involved in the workpackage (Nijmegen, Wurzburg, PSI ~ 10 min per partner)
- 16:30-16:40 Summary of the criticism. Development of updated time-table for deliverables
16:40-17:20 Workpackage 4
- 16:40-16:50 Application perspectives from Seagate
- 16:50-17:10 Application perspectives from NXP
17:10-17:30 Workpackage 5. Management
17:30-18:00 Conclusions and closure