Notes from meeting:
- LLRF group inform that it is important to upgrade the SALO system of TWLHA
- Upgrade cost in the 10s of kCHF
- current system is partially damaged
- Important if we want to operate with Beam.
- Nir to speak with Kurt after meeting to see how to proceed before the racks are assigned.
- Pressurized air. Need to be pulled to diagnostics screen.
- Feed-through flange is not suitable for UHV.