•James:
•Delay on drawing approval for box plates-> expected end of week feedback
•Target flange next for review
•Target door under review, next to order
•Ceramics from K.J Lesker, quote expected end of week
•Rob House
•Florain to release the drawings for chamber- busy with HIMB
•Table design to be reviewed for release by us next week, expected costs are 3kchf for structure and 5 for the top
•High current contacts are approved and under construction, expected august
•Reinhard:
•Laser interlocks requires the HSE to know the locations of all the services in the room
•PSI have an existing solution for the beam blocker but requires modification to operate with the higher power lasers. Needed for Q3 2027
•Expected to purchase multiple lasers, has been reviewing the market for suppliers
•Requires a large lockable place to store the laser before construction of the lab
•Sven:
•Ordering racks for the vacuum and the LabVIEW controls
•Using recycled racks to save costs. 1x 600mm and 1 x800mm depth full height racks
•Inductive heating system from SINQ that may be of use to TATTOOS. To be seen later
•Davide:
•Remi away for month and will be running tests in TRIUMF
•Pushing to fabricate 10 targets for testing
•Workshop is keen to work on this project
•Tim:
•No updates this week
•Group:
•Not in favour of AI transcripts, will not be used
There are minutes attached to this event.