This presentation outlines the System Installation and Final Integration (SIFI) scope supporting the Accelerator Storage Rings (ASR) Subproject. The focus is on the installation and integration of Electron and Hadron Storage Ring systems within the existing 3.8 km beam line tunnel and the new and existing service buildings at Brookhaven National Laboratory.
The talk details installation responsibilities across major technical systems, including normal and superconducting magnet assemblies, snake magnets, vacuum systems, RF and SRF systems, cryogenic distribution (2K and 4K), instrumentation, power supplies, and associated electronics.
Key dependencies, such as RHIC Removal & Repurposing activities, new and existing service building readiness, utility availability, and CD-3A cryogenic deliverables, are discussed. The presentation also highlights bottom-up Basis of Estimate (BOE) development, installation sequencing, safety and work control processes, and configuration management practices.