Elettra 2.0 Project is entered the "Installation Phase" for the Storage Ring. The "Removal Phase" ended in November 2025 following the start of the "Dark Period" on July 2025.
Go to contribution page
The talk is focused on the many expected and - in some cases - unexpected issues related to the logistics, handling, and planning activities for the removal and the installation of the Storage Ring and the beamline hutches. -
Simon Barrière (CERN)05/05/2026, 09:25Oral
The High-Luminosity Large Hadron Collider (HL-LHC) project involves a major upgrade of the cryogenic infrastructure supplying helium to the final focusing regions of the ATLAS and CMS experiments. The integration of new superconducting components requires the complete removal of the existing cryogenic systems installed in the long straight sections at Points 1 and 5, covering a total length of...
Go to contribution page -
Melissa Harvey (Oak Ridge National Laboratory - Spallation Neutron Source)05/05/2026, 09:50Oral
Waste beam from the Spallation Neutron Source’s (SNS) injection process is steered to the Ring Injection Dump (RID). The history of the design and installation of the RID is convoluted and included late design changes requiring post-installation machining. In 2023, the RID proton beam window and beamstop were replaced, in part to support the installation of the RID Imaging System, which...